We are excited to share the great progress of our new secondary school in Tal, Nepal, in partnership with Pahar Trust Nepal.

Works to date include the digging of foundations and the casting of the concrete ground slab and columns. Bricks have been delivered to site and ground floor walls are being built.

The original Shree Bhanu School was damaged in floods and a landslide in June 2021. The building was deemed structurally unsafe and beyond repair. The new school is being built at a nearby site away from potential future floods.

Working with our local partner, this new building will provide 14 classrooms and also include a clean water supply and toilets.

Thanks to a generous donation and a contribution from the Nepalese Government the money for the project is already in place. Works started on site in December 2023. The project is  estimated to take one year to complete.

The estimated total cost is £98,700.